Pre-Drywall Inspection Form

Please answer each of the following.

Poly > 80%

Installation will be reviewed for the following

  • Air barrier is complete
  • Support at all joints
  • Overlap - 4" minimum
  • Thick beads of caulking on face of framing
  • Penetrations sealed at attic hatch, electrical, plumbing and HAVC

All duct work connected and sealed

Insulation > 80%

  • Air barrier contact on all sides
  • Supported and aligned
  • No compression resulting in gaps in framing spaces

R/O Sealed

  • Window and door opening sealed - spray foam or backer rod/caulking

Rim joist sealed

Installation will be reviewed for the following

  • Spray foam complete
  • Spray foam connection to framing wall is complete
  • No gaps or voids in spray foam
  • Thick beads of caulking on face of framing
  • Plumbing & HAVC Penetrations blocking and well sealed around entire circumference

Spray foam complete

  • Including plumbing % electrical